Tomorrow, Tuesday it’s a month since we got back to Lefkas and progress seems to have been painfully slow, but on Friday we got the insurer’s approval to proceed with repairs and our repair contractor, YachtPaint, started today. In fact they were on the job by 0830 – the earliest we can ever recall a contractor turning up for work on Envoy. Let’s hope that’s a good omen!
Tue 25/4: arrive Lefkas the day of fire
Thu 27/4: meet assessor and YachtPaint manager
Fri 28/4: receive quote from YachtPaint to clean Envoy of fire debris and forward to insurer
Sun 30/4: organise accommodation and rental car as we can’t live on board
Tue 1/5: insurers approve cleaning quote
Thu 4/5 – Fri 5/5: crane hoists RHIB down from Envoy and YachtPaint clean Envoy so damage can be properly inspected
Tue 9/5: assessor returns for full joint inspection with YachtPaint and us. Degree of damage identified and YachtPaint to quote for total repair
Wed 10/5: original expected cruising start date
Fri 12/5: meet YachtPaint at Envoy to discuss repair quote
Sat 13/5: Sailand and I list all rigging needing replacement
Mon 16/5: Sailand remove all broken windows and portholes and send to glass factory. I obtain quote for 3 soot-damaged covers that need replacing. YachtPaint’s quote received and forwarded to assessor, who sends to insurer
Tues 17/5: Sailand do a considerable amount of non fire-related work
Fri 20/5: insurer’s verbal approval to proceed obtained. YachtPaint advised
Mon 22/5: insurer’s written approval expected. YachtPaint start work
Sat 24/6: projected completion date
Fri 30/6: projected launch and sea trial date
Tues 4/7: projected departure and start cruising date